Project Scope
- NSCRP CP02 is 14.009 KMs. from Brgy. Taal, Bocaue to Brgy. Bulihan, Malolos
- Project duration is July 2, 2019 to January 1, 2023
- Work schedule: 24 hrs.
3 Stations
- Malolos Station – Brgy. Bulihan
- Guiguinto Station – Brgy. Tikay
- Balagtas Station – Brgy. Borol 1st